Project
Scott's
Bridge Road Relocation
Client
Anderson
County
Anderson, South Carolina
Scope
Relocation
of a county road between SC Highway 81 and Interstate Highway 85 to
accommodate construction of a new manufacturing facility.
Project design time was only 30 days in order to accommodate
commitments to the industry. Design
of the 2,850 feet relocated road included demolition, earthwork, storm
drainage, paving and traffic control.
The project was designed to SCDOT standards and specifications.
Pavement design and turning clearances for truck traffic were
significant considerations.
Cost
$150,000
Completed
September
1990 |