Project
Alterations
and Additions to
Centerville Elementary School
Client
Anderson
School District Five
Anderson, South Carolina
Scope
Alterations
to approximately 33,770 square feet of classrooms, kitchen and
cafeteria, lobby, various office spaces, toilet facilities and library
spaces were necessary. In order to create a new main entry for the
school, an existing loading area was converted. All existing
electrical, mechanical and roofing systems were replaced.
New construction additions included approximately 36,620 square feet of
new classrooms, storage rooms, toilet facilities, a library, a work
room, a multi-purpose room and stage area. Approximately 3,120 square feet of
covered walkways and canopies were added as well as 4,300 square feet of
Kindergarten play yard.
Cost
$2,914,000
Completed
December
1990 |