Project
New
Detention Center
Client
City of
Anderson
Anderson, South Carolina
Scope
Phase I of
the City of Anderson City Hall improvements included the construction of
a three-level reinforced concrete structure of approximately 21,227
gross square feet with an unfinished lower level intended to house
the future city council and municipal court facilities (to be completed
in Phase II). The upper two levels of the center, the main floor
and mezzanine, house additional jail facilities for the City of
Anderson. These areas consist of 48 single and double occupancy
cells, a master control room, toilets, showers, storage spaces, and
associated facilities. Site work included the relocation of an
existing driveway, construction of reinforced concrete retaining walls,
an entrance areaway, courtyard, storm drainage, and the relocation of
utility systems.
Cost
$4,270,000
Completed
1999 |